Construction set to begin on Elliott Road in West Kelowna
Pedestrian improvements to start on Elliott Road: Rendering (Image Credit: City of West Kelowna)
Motorists travelling along Elliott Road in West Kelowna can expect traffic delays starting Monday as crews begin pedestrian safety improvements.
The work will focus on installing a retaining wall along the south side of Elliott Road, between the cemetery entrance and Smith Creek Road.
Construction is expected to continue into early December, weather permitting. Single-lane alternating traffic will be in place around the clock from Monday to Friday, with two-way traffic restored on weekends.
Drivers should expect brief delays between 7 a.m. and 5 p.m. Access to driveways, businesses and emergency services will be maintained. Traffic leaving the cemetery will be required to turn right.
The work is part of a $4.5-million project that includes a new multi-use pathway, street lighting, road upgrades, improved cemetery access and stormwater infrastructure.
Further improvements are planned into 2027, with longer-term upgrades between Solar Road and Butt Road targeted for completion by 2031.
The city is asking motorists to slow down, follow posted speed limits and obey traffic control signs.